Tennessee Processing Center

Nashville, TN

Tennessee Processing CenterTennessee_Processing_Center
Bank of New York
Nashville, TN
Project Size 160,000 SF

Project Description:

Facility Dynamics Engineering was retained by Tishman Construction Company to provide mechanical systems commissioning services for the Bank of New York’s 160,000 sf Tennessee Processing Center. Our scope of commissioning (Cx) activities included HVAC systems serving the critical data center operations and the common comfort applications.

Systems Commissioned include:

  • HVAC Systems
    • Computer Room Air Conditioning Units
    • Redundant Condenser Water System
    • Water Source Heat Pumps
    • Cooling Tower
    • Chillers
    • Exhaust Systems
    • Fuel Oil Systems
  • Building Automation System
  • Electrical Systems
    • Emergency Generators
    • Dual Electric Utility Feeders
    • Switchgear